Renovations run in a fixed order because each trade covers the work of the one before. Strip-out comes first, then structural work. Services follow inside walls, floors and ceilings: drainage, water, electrical and air-conditioning. Wet areas are waterproofed, and the membrane should be tested while it is still exposed. Screeds, plaster and ceilings close everything in. Then come tiles and flooring, joinery installation, stone tops templated once the walls are finished, painting, and finally sanitary ware, fittings and lighting.
The order explains why late changes cost more. Moving a socket after plastering means cutting into a finished wall, and moving a basin after tiling means breaking tiles and possibly the waterproofing under them. Settle positions on the drawings before services go in. Our six-stage process shows where those decisions are made.